Project: | Asbestos Removal and Demolition of St Martins Hall |
Client: | WSP Group/HCA |
Location: | WSP Group/HCA |
Date: | February 2014 - March 2014 |
Ron Hull Demolition Ltd were awarded the contract for the Asbestos Removal and Demolition of St. Martins Hall, Grimsby through competitive tender.
The project was planned carefully by Ron Hull's Management Team and in consultation with the Site Team. Works commenced with the soft strip, where Demolition Operatives removed any loose items including cosmetic elements, tables, chairs, desks, doors, door frames, skirting boards, suspended ceilings and flooring. The waste materials were deposited directly into the skips located adjacent to the building entrance ready to be sent back to the Ron Hull Group recycling centre in Rotherham.
Once the soft strip had been completed, Ron Hull Demolition's specialist Asbestos Removal team were employed on site for the safe removal of any asbestos containing materials as per Risk Assessments and Method Statements.
The first phase of the demolition utilised the wheeled excavator with grab attachment to open up the west end gable wall, working from top down. All waste arisings were separated, processed and loaded into skips for disposal. Working into the building the excavator removed the wooden floor sections and then continued with the next stage of roof followed by side walls and then floor area. Progressing through the structure the machine remained on the footprint of the building demolishing the remaining structure.
To the delight of the Client, the project was completed within budget on time and most importantly without incident.
Commercial & public building demolitions by Ron Hull Ltd – Experts in recycling, remarking & waste management, we are Yorkshire’s leading demolition contractors
Public buildings are often by necessity placed close to vital local amenities and infrastructure. They often intersect with residential areas, busy commercial areas, and contain a high density of utilities. Demolition in such an environment comes with its own unique challenges, and may be affected by strict deadlines based on commercial or public use of these nearby spaces. Equally, different buildings have different purposes and each project might come with a unique list of requirements. The last thing residents, service users, local authorities and clients want is for the project to indirectly disrupt the community.
Ron Hull Ltd have the expertise, based in decades of experience, to carefully balance the need for a dynamic, efficient, cost-effective demolition process with the demands of operating in a modern urban setting. For over two decades we have undertaken complex demolition projects that often have required our planners, managers, operators and technicians to go above and beyond for the sake of a job well done. We regularly earn praise from clients who have seen what we do, and the extra steps we take to ensure projects are finished, not just on time and under budget, but in line with the highest standards of professional excellence.
Learn more about some of our past commercial & public building demolitions:
Asbestos Removal & Demolition of Minsthorpe Swimming Pool
Asbestos Removal & Demolition of Lodge Community Centre
Demolition of Liquid Nightclub
Demolition & Asbestos Removal of Foxhills Technology College
Demolition of Maltby Sports Centre
Demolition of Gloystarne Building
Demolition of 18 no. High Rise Tower Blocks
From our roots in South Yorkshire, to becoming a highly experienced, trusted, industry leading demolition contractor, Ron Hull Ltd has never wavered from its founding principle of providing complete, eco-friendly solutions from the first day on site to the last. We can recycling and remarket almost all of the waste product from our products, saving our clients’ money and ensuring nothing ends up in landfill. We take pride in going far beyond many of our competitors in our ambitious environmental & sustainability policies. We ensure as far as possible that all possible materials are recovered and repurposed, recycled or remarketed, and we welcome enquiries from prospective clients into how we can deliver a seamless demolition with a minimal environmental footprint.
Our ability to deliver smooth, cost effective and environmentally responsible demolition services makes us first choice for many local authorities and companies who wish to minimise disruption and lessen the environmental impact of their project, as well as reducing costs.
With satisfied customers across the UK and an industry leading reputation as a safe, efficient, professional and innovative demolition company, why not speak to us about the ways our team can assist in your project.
For more information on any of our previous projects or the particulars of how we approach each demolition challenge, please feel free to contact our team at our office in Rotherham, Yorkshire.