Client Testimonials

Ron Hull Demolition Ltd have successfully carried out such Projects as the Dismantling of an Arsenic contaminated Plant for ICI Sever side, demolished two British Sugar Plants, completed shutdown works for Corus on blast furnace, stoves and furnaces, and recently completed a six year dismantling/demolition project for Huntsman, Grimsby.

Please see Projects for further information on the projects carried out by Ron Hull Demolition Ltd.

Below are a few of Ron Hull Demolition Ltd’s customer testimonials, offering witness to our unrivalled, professional experience in the demolition arena.


Following the successful completion of the demolition and site clearance of the Roughdales Factory, I would like to thank you on your company's performance.

As well as a very good general peformance, I am pleased to advise you that the overall health and safety performance of your Company met the standard required by Ibstock Brick Limited. This reference will be placed on IBL internal contractors register which is accessible to all sites.

I would make pafticular comment on the good response to IBL systems and the excellent site superuision you provided at all times.

As with any project of this nature and magnitude there were minor issues which were all dealt with promptly and efficiently. Please pass on my thanks to all concerned.

IBSTOCK BRICK LTD.


Ron Hull Demolition Ltd., were employed as the Principal Contractor for the Demolition, Site Clearance and remediation of the former Ardagh Glass production facility in Worksop, UK.

The works required the demolition numerous buildings and RC structures across the 1.4 acre site; demolition (using explosive methods) of a 200 feet chimney stack adjacent to a highly trafficked rail line; removal of a 200 tonne glass furnace and associated contaminants; safe removal of significant amounts of reportable asbestos materials; clean up areas of TPH contamination; landscaping of the cleared areas.

The contract was undertaken under the NEC form of contract and had a value of between 0.75 - f1.0M, and was completed 1 week ahead of the Completion date.

The works were executed to a high standard, Health and Safety management and methods were more than satisfactory, especially when the nature and awkwardness of some work activities is considered.

We would have no objection to employing Ron Hull Demolition Ltd., on any of our future projects.

FAIRPORT ENGINEERIING LTD.


Please may I take this opportunity to thank George Brabham and his team for their major contribution to the successful completion and early handback of the recent 38 hour possession at Doughty Road.

George and his demolition team carried out the works in a professional and competent manner with a safety first approach.

Although the demolition works were far from straight forward, the works was carried out to the programme thus allowing follow on activities the best chance of success.

Once again, please pass on my appreciation to all those concerned and especially George, who is a credit to your company.

C SPENCER LTD.